Chennai City River Conservation Project

Government of Tamil Nadu jointly with Ministry of Environment and Forest (National River Conservation Directorate), Government of India undertook a comprehensive study examining the cause of pollution of the water ways and its impact on the environment and formulated "Chennai City River Conservation Project".

Chennai City has six waterways viz. Adyar, Cooum, Buckingham canal, Otteri Nullah, Captain Cotton Canal and Mambalam Drain.

Essentially these river functions as a flood carriers and have flows for about 2 months during monsoon. During the remaining part of the year the flow is mainly due to discharge of treated, partially treated and untreated sewage through about 311 out falls meant for storm water discharge, resulting in accumulation of large volume of sludge and formation of sand bar in the mouth of rivers. These overflows have created significant problems for flood protection system, storm water drain net works and public health leading to over all environmental degradation. Hence, long term objective of the project is to holistically improve the waste water or sewage disposal network so as to prevent noxious substances from reaching the water ways.

The project aims to provide the following.

  • Interceptor sewers along River banks.
  • Increasing Pumping Potential of Sewage Pumping Stations.
  • To achieve 100% effluent Standards of Sewage Treatment Plants as per the Tamil Nadu Pollution Control Board's norms.
  • To increase the coverage of Agro-Forestry with treated sewage.
  • To set up nursery of saplings of Agro-Forestry at Sewage Treatment Plants.

Moreover, the capacity of the existing sewer system has become grossly inadequate and is in need of major improvements, if the discharge of untreated and partially treated sewage into the City Water Ways is to be prevented.

The components pertaining to interception, diversion and treatment of sewage costing Rs.720.15 crores (prevention of raw and untreated sewage flow to water courses) would be implemented by CMWSSB and supported by the Govt. of India, Ministry of Environment and Forests, National River Conservation Directorate (NRCD) on the following funding pattern:

1. Grant from NRCD - Rs.491.52 Crores

2. Internal generation by CMWSSB - Rs.228.63 Crores

This comprises of "Interception, Diversion and Treatment of Sewage" in all the five zones and providing additional 264 mld capacity of sewage treatment plants in four locations. The works are planned to be executed in 16 Packages.

Out of the total CCEA approved cost of Rs.491.52 crores, the works were taken up under 16 Packages at an estimated cost of Rs.382.24 crores with a savings of Rs.109.28 crores.

Subsequently, NRCD has approved the Additional Works amountings to Rs2215.78 lakhs for expansion capacity and strengthening of sewerage system covering the necessary stretches utilizing the savings of Rs.109.28 crores under CCRCP. The project cost of these additional works has to be shared by the Government of India and Government of Tamilnadu in 70:30 ratios repectively.


Package - 1A1:

Interceptor works at Besant Nagar and Thiruvanmiyur, Pumping Stations at Perungudi, Velachery and Gandhi Nagar, and pumping main for Gandhi Nagar.

Contractor: M/s. VA Tech Wabag Ltd.
Contract Value: Rs.15.49 Crores
Date of commencement of work: 11.05.2001
Period of completion: 30 months
Length of Interceptor: 746 m
Length of Pumping Main: 108 m
Stage of work: 100% of civil works completed
100% of Mech. & Elec., works completed
Package - 1A2:

Laying RCC gravity sewers from Madhaya Kailash along CPT Road, Taramani and Old Mahabalipuram Road upto Perungudi STP.

Contractor: M/s. Simplex Concrete Piles (I) Ltd.
Contract Value: Rs.17.76 Crores
Date of commencement of work: 11.05.2001
Contract Period: 30 months
Length of Gravity Main: 6929 m
Stage of work: 100% of pipe laying works completed
Package - 2:

Interceptor works for North Mylapore and Ice House pumping station, pumping main and gravity main for Ice House.

Contractor: M/s. Cipta Wawasan Maju Engg
Contract Value: Rs.20.19 Crores
Date of commencement of work: 05.03.2001
Contract Period: 30 months
Length of Interceptor: 9192 m
Length of Pumping Main: 2950 m
Length of Gravity Main: 2600 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100% of Pipelaying works completed.
Package - 3:

Interceptor works at Kasimedu, North Wall Road, Tondiarpet-A, B & E pumping station and pumping main for Kasimedu.

Contractor: M/s. Ramky Engineers Pvt. Ltd.
Contract Value: Rs. 8.97 Crores
Date of commencement of work: 14.02.2001
Contract Period: 30 months
Length of Pumping Main: 7625 m
Length of Gravity Main: 2107 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100% of Pipelaying works completed.
Package - 4:

Expansion of capacity of interceptor system in South Mylapore, Adyar (old) and expansion of capacity of pumping stations at Nandanam, Adyar and Guindy.

Contractor: M/s. Nagarjuna Constn. Co. Ltd.
Contract Value: Rs.25.81 Crores
Date of commencement of work: 05.03.2001
Contract Period: 30 months
Length of Interceptor: 8375 m
Length of Pumping Main: 3322 m
Length of Gravity Main: 1117 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100% of Pipelaying works completed.
Package - 5A1:

Expansion of capacity of K.K.Nagar ‘B’ and Nesapakkam pumping stations.

Contractor: M/s. V.A.Tech Wabag Ltd.
Contract Value: Rs.7.54 Crores
Date of commencement of work: 11.05.2001
Contract Period: 30 months
Length of Interceptor: Completed
Length of Pumping Main: Completed
Length of Gravity Main: Completed
Stage of work: 100% of civil works completed
100% of Mech. works completed.
Package - 5A2:

Expansion of capacity of Kodambakkam, Ekkattuthangal interceptors and replacement of Nesapakkam gravity sewers.

Contractor: M/s. Simplex Concrete Piles (I) Ltd.
Contract Value: Rs.9.57 Crores
Date of commencement of work: 11.05.2001
Contract Period: 30 months
Length of Interceptor: 2495 m
Length of Pumping Main: 716 m
Length of Gravity Main: 3332 m
Stage of work: 100% of pipe laying works completed
Package - 6A:

Expansion of capacity of interceptor in Thomas Road, T.Nagar, South Boag Road and expansion of capacity of Pumping Station in Thomas Road and construction of new Pumping Station at South Boag Road with Pumping Main.

Contractor: M/s. V.A. Tech Wabag Ltd.
Contract Value: Rs.12.12 Crores
Date of commencement of work: 12.09.2003
Contract Period: 30 months
Length of Interceptor: 6476 m
Length of Pumping Main: 3844 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100 % of Pipelaying works completed.
Package - 7:

Expansion of capacity of interceptor in Thomas Road, T.Nagar, South Boag Road and expansion of capacity of Pumping Station in Thomas Road and construction of new Pumping Station at South Boag Road with Pumping Main.

Contractor: M/s. Lanco Construction Ltd.
Contract Value: Rs.12.68 Crores
Date of commencement of work: 12.03.2001
Period of Completion: 30 months
Contract Period: 30 months
Length of Interceptor: 6527 m
Length of Pumping Main: 1860 m
Length of Gravity Main: 869 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100 % of Pipelaying works completed.
Package - 8:

Interceptor work in Kodambakkam and Arumbakkam, expansion of capacity of Arumbakkam and Sydenhams Road pumping stations, gravity main for K.K.Nagar and pumping main for Sydenhams Road.

Contractor: M/s. Lanco Construction Ltd.
Contract Value: Rs.16.44 Crores
Date of commencement of work: 12.03.2001
Contract Period: 30 months
Length of Interceptor: 7290 m
Length of Pumping Main: 717 m
Length of Gravity Main: 397 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100 % of Pipelaying works completed.
Package - 9A:

Interceptor work in Kodungaiyur Phase I and M.K.B.Nagar catchment areas and expansion of capacity of Pumping Stations at Kodungaiyur Phase I, M.K.B.Nagar, Javkhar Nagar, Melpattadai and Periyar Nagar.

Contractor: M/s. Vishwa Constructions.
Contract Value: Rs.6.40 Crores
Date of commencement of work: 21.08.2003
Contract Period: 18 months
Length of Interceptor: 431 m
Length of Pumping Main: 4244 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100 % of Pipelaying works completed.
Package - 10:

Expansion of capacity of interceptors in the Purasawalkam catchment area and expansion of pumping capacity of Sembium pumping station and Purasawalkam pumping station.

Contractor: M/s. Simplex Concrete Piles (I) Ltd.
Contract Value: Rs.25.63 Crores
Date of commencement of work: 12.03.2001
Contract Period: 30 months
Length of Interceptor: 6365 m
Length of Pumping Main: 3430 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100 % of Pipelaying works completed.
Package - 11:

Expansion of capacity of interceptors at Shenoy Nagar, Anna Nagar-A, B & C, expansion of pumping capacity of Anna Nagar-A, B & C pumping station and expansion of capacity of pumping main/gravity sewer for Anna Nagar-B.

Contractor: M/s. V.A. Tech Wabag Ltd.
Contract Value: Rs.12.86 Crores
Date of commencement of work: 26.03.2001
Contract Period: 30 months
Length of Interceptor: 3415 m
Length of Pumping Main: 1510 m
Length of Gravity Main: 826 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100 % of Pipelaying works completed.
Package - 12:

Laying interceptors at Villivakkam Sector-A and Sector-B, laying of pumping/gravity main from Villivakkam Phase-II and laying of pumping mains from Villivakkam Sector-A and Sector-B pumping stations and expansion of capacity of pumping stations at Villivakkam Sector-A, Sector-B and Phase-II.

Contractor: M/s. Vishwa Constructions.
Contract Value: Rs.4.73 Crores
Date of commencement of work: 30.03.2001
Contract Period: 30 months
Length of Interceptor: 230 m
Length of Pumping Main: 3895 m
Length of Gravity Main: 1226 m
Stage of work: 100% of civil works completed
100% of Mech. works completed
100 % of Pipelaying works completed.
Package - 13:

Design, Build and Operate 54 mld capacity Sewage Treatment Plant at Perungudi.

Contractor: M/s. V/A Tech Wabag Ltd.
Contract Value: Rs.3269.89 Lakhs
Date of commencement of work: 30.09.2003
Contract Period: 18 months
All works completed and commissioned.
Package - 14:

Design, Build and Operate 60 mld capacity Sewage Treatment Plant at Koyambedu.

Contractor: M/s. Batliboi.
Contract Value: Rs.2504.84 Lakhs
Date of commencement of work: 03.09.2003
Contract Period: 18 months
All works completed and commissioned.
Package - 15:

Design, Build and Operate 40 mld capacity Sewage Treatment Plant at Nesapakkam.

Contractor: M/s. BHEL.
Contract Value: Rs.1947.88 Lakhs
Date of commencement of work: 03.09.2003
Contract Period: 18 months
All works completed and commissioned.
Package - 16:

Design, Build and Operate 110 mld capacity Sewage Treatment Plant at Kodungaiyur.

Contractor: M/s. V/A Tech Wabag Ltd.
Contract Value: Rs.3827.73 Lakhs
Date of commencement of work: 03.09.2003
Contract Period: 18 months
All works completed and commissioned.