Complaint Cell: + 4567 4567

CCRCP Additional Works

STATEMENT SHOWING THE STATUS OF ADDITIONAL WORKS

Sl. No. Name of the work Scheme wise details of works awarded Date of commencement Status
1. Expansion of capacity and strengthening sewerage system - Ayanavaram Interceptor in Otteri Nullah Basin Laying 350 to 900mm dia DI pipe for a length of 2103m Work to be taken up.
2. Expansion of capacity and strengthening sewerage system - Vyasarpadi Interceptor in Otteri Nullah Basin Laying 350 to 900mm dia DI pipe for a length of 2296m Contractor terminated
3. Expansion of capacity and strengthening sewerage system - Nammalvarpet Interceptor in Otteri Nullah Basin Laying 350-700mm dia DI pipes for a total length of 1675m 31.12.08 To be foreclosed due to technical feasibility
4. Expansion of capacity and strengthening sewerage system - KK Nagar & Padmanabha Nagar Interceptor in Adyar River Basin Laying 400-600mm dia DI pipes for a total length of 700m 01.12.08 Contractor terminated
5. Expansion of capacity and strengthening sewerage system - Dimmasamy Dharga Interceptor & Villivakkam Phase-I pumping station in Otteri Nullah Basin Laying 400-500mm dia DI pipes for a total length of 205m & const. of suction and screen well for the PS 09.02.09 Work completed.
6. Expansion of capacity and strengthening sewerage system - Langs Garden Interceptor in Cooum River Basin Laying 400-600mm dia DI pipes for a total length of 898m 31.12.08 Work is in progress
7. Expansion of capacity and strengthening sewerage system - Thiruvanmiyur and Besant Nagar-II Pumping Station in Buckingham Canal Basin Constn. Of suction and screen well at Thiruvanmiyur PS. Constn.of suction and screen well, Office building and toilet block and pumping main for a length of 900m for Besant Nagar II PS 20.05.09 Work completed
8. Expansion of capacity and strengthening sewerage system - Seethammal Colony and Foreshore Estate Pumping Station in Adyar River Basin Constn. of suction and screen well at Seethammal PS. Constn.of suction and screen well and pumping main for a length of 810m for Foreshore Estate PS 18.09.09 Work completed
9. Expansion of capacity and strengthening sewerage system - Jawahar Nagar & Melpattadai Interceptor in Captain Cotton Canal Basin Laying 350-400mm dia DI pipes for a total length of 1064m 02.01.09 Work completed
10. Expansion of capacity and strengthening sewerage system Pumping Station at Greams Road in Area-VII. Constn.of suction and screen well, Office building and panel board room with store room for Greams Road PS 09.02.09 Work completed

7. CONSTRACTION OF SEWAGE TREATMENT PLANT:

  • It is proposed to construct STP at Sholinganallur and Navalur.
  • DPR under preparation for the construction of STP and Pumping Mains.
  • Tender floated for Navalur STP and the tender due on 12.12.2009.

8. CONSTRUCTION OF PUMPING STATION

The proposal for the construction of pumping station in the following locations.

  • Sholinganallur
  • Navalur East
  • Okkiam Thoraipakkam West
  • Okkiam Thoraipakkam East
  • Perungudi West
  • Ekattur West
  • Kazhipattur
  • Karapakkam
  • Semmenchery East
  • Semmenchery West
  • Navalur West

Preparation of DPR for the Pumping Station is in progress.

Back